BELLA VISTA POA TRAFALGER FIRE SITE
The following major activities were completed today or are underway by the Bella Vista Property Owners Association, pursuant to the May 3, 2019 Settlement Agreement:
- Revised and finalized the Air Monitoring, Noise Monitoring, and Hazard Communication Plan
- Revised and finalized the Phase I Remedial Action Plan
- Prepared for mobilization to the Site, starting May 15, 2019
- Submitted necessary permit applications to ADEQ to start construction
This work has been completed in accordance with the requirements of the Settlement Agreement.
May 14, 2019
Second In the Know special edition regarding Trafalgar Fire questions. https://youtu.be/Q8ZgJHb-ceY
Bella Vista POA Releases 2nd In the Know Video Regarding Trafalger Road Fire
LATEST INFORMATION:
May 14, 2019 – ADH’s latest review of particulate matter air monitoring near the Trafalgar Road fire for dates April 25-May 8 has been posted: https://www.adeq.state.ar.us/bella-vista/pdfs/20190514-adh-pm-evaluation.pdf